Summary of Results for March 19, 2018 Supplemental RFP

Period of Delivery June 1, 2018 - May 31, 2019
Benchmark Price N/A
Number of Registered Bidders 2
% of PIPP Load to procure in the RFP 100%
% of PIPP Load procured in the RFP 100%
Lowest bid price $51.34 per MWh


Summary of Results for April 11, 2017 Supplemental RFP

Period of Delivery June 1, 2017 - May 31, 2018
Benchmark Price N/A
Number of Registered Bidders 4
% of PIPP Load to procure in the RFP 51%
% of PIPP Load procured in the RFP 51%
Lowest bid price $50.69 per MWh


Summary of Results for May 3, 2016 RFP

Period of Delivery June 1, 2016 - May 31, 2017
Benchmark Price $48.34 per MWh
Number of Registered Bidders 3
% of PIPP Load to procure in the RFP 17%
% of PIPP Load procured in the RFP 17%
Lowest bid price $44.98 per MWh